A regulatory board’s rejection of a permit for a large solar farm in southwestern Ohio has “essentially rewritten” state law to give local governments veto power over clean energy projects, an attorney for the project’s developer argued last week before the Ohio Supreme Court.
The Ohio Power Siting Board’s 2022 decision denying Vesper Energy the right to build a 175-megawatt solar facility in Greene County is the subject of a high-stakes legal challenge with potentially “devastating” consequences for the state’s ability to grow its electricity generation capacity, the developer’s attorney said.
“All of Ohio’s energy infrastructure will be affected by this decision,” said Michael Settineri, who represents Vesper’s Kingwood Solar project, in an oral argument before the court on March 13.
The company claims the siting board failed to follow state law in its analysis of whether its project is in the public interest — one of eight criteria that power generation projects must meet to receive a site permit. Instead of evaluating the merits of opponents’ arguments, the board used the mere existence of local government opposition as reason to deny the permit, Kingwood Solar’s attorney said.
A lawyer for the Ohio Power Siting Board argued that it has wide discretion to make policy judgments and that members used “a broad lens” to make their decision.
Local criticism has killed multiple Ohio solar projects
Renewable energy permitting has become especially difficult in Ohio over the last four years. A 2021 law lets counties block most new utility-scale wind and solar energy projects before they even get to the Ohio Power Siting Board. Others, like Kingwood Solar, have been denied based on local opposition, even though they are exempt from that part of the law because they filed permit applications or got in the grid operator’s queue prior to the legislation’s passage.
In 2022, the board found that the proposed Kingwood Solar facility met all the other legal requirements for a permit, yet it concluded “that the unanimous opposition of every local government entity” bordering the project was “controlling” on the public interest question. The board denied the permit.
Settineri urged the court to reverse the Ohio Power Siting Board’s decision, arguing that it was clearly not supported by evidence. And, as a legal matter, the board essentially rewrote the law for granting or denying a permit in a way that gives local governments control that they shouldn’t have, he said.
Justice Jennifer Brunner noted another part of Ohio law that says local governments can’t require their own consent for the construction of power facilities. When the board’s Kingwood Solar decision said “that unanimous opposition is controlling, that actually infers that consent is required by the locality. Isn’t the board violating the statute?” she asked Settineri.
He answered,“The way I read the board’s decision, it is giving the local governments veto power … contrary to the concept of a state siting regimen.”
Renewable developer says Ohio regulators failed to consider evidence
The board’s ruling was also “internally inconsistent,” Settineri said. The board claimed it gave weight to the “vigor and rationale” of local governments’ objections, which included worries about visual impacts, preservation of agricultural land, and construction.
But the solar developer presented experts and other evidence addressing those topics during a 2022 hearing in the case. It was also willing to accept permit conditions to minimize any impacts. As a result, the board sided with the developer on those issues in its findings on statutory criteria other than public interest, including considerations related to agriculture and the environment, Settineri said.